|
Fast Forward
Northern Virginia's Route 28 project
speeds toward completion
By Bruce Buckley
Fueled by a public-private partnership that allows the
design and construction team considerable control, $200
million of improvements along the Route 28 corridor are
on schedule to be completed in less than half the time of
traditional design-bid-build methods.
|
|
|
The Route 625
interchange, pictured here under construction, is a
partial cloverleaf interchange and a four-lane bridge
carrying Route 625 over Route 28 with a flyover ramp
from northbound 28 to westbound 625. The heavy flow
of westbound traffic is split by two exits - a loop
ramp (bottom right) that handles vehicles heading to
AOL and the flyover ramp (top left) that serves through-traffic
heading to Ashburn.
|
Things move quickly in Loudoun County, Va., these days, and
the construction team on the Route 28 corridor project has
embraced that spirit.
During the past decade, Loudoun has emerged as the fastest-growing
county in the United States, and the strain can be felt along
the crowded lanes of Route 28 - a major artery cutting across
the eastern edge of Loudoun into neighboring Fairfax County.
Since October 2002, general contractor Clark Construction
of Bethesda, Md., and its subsidiary, Shirley Contracting
of Lorton, Va., have been working with Virginia DOT and designer
Dewberry & Davis of Fairfax, Va., to design and build
nearly $200 million in improvements along Route 28 between
State Route 7 and Interstate 66.
Halfway through the project's tight four-year schedule, the
partnership, collectively known as Route 28 Corridor Improvements
LLC, is right on course.
The fast-track project is the first in northern Virginia
developed through the Public-Private Transportation Act of
1995. Ultimate plans call for the creation of a 14-mi. limited-access
highway, which includes widening it from six to eight lanes,
removing 15 traffic signals and adding 10 interchanges. Six
of those interchanges are funded under the current phase.
Substantial completion is expected in November 2006 with final
completion in May 2007.
Under terms of the contract, the construction team is overseeing
most major aspects of the process, including design, construction,
utility relocation, permitting and right-of-way acquisition.
Adding right-of-way and utility duties into the design-build
process has paid the biggest dividends, said Susan Shaw, Route
28 project manager for VDOT.
"By including both of those we've seen a tremendous
improvement over our traditional project schedule," she
said.
Unclogging the backups
Construction of the Route 625 interchange, the project's
largest intersection, put the team's abilities to the test.
In recent years, the existing intersection had created some
of the worst backups along Route 28 as commuters turned on
westbound 625 toward AOL's corporate park and neighboring
Ashburn. The design solution was to create a partial cloverleaf
interchange and a four-lane bridge carrying Route 625 over
Route 28 with a flyover ramp from northbound 28 to westbound
625. The heavy flow of westbound traffic is split by two exits
- a loop ramp on the right that handles vehicles heading to
AOL and the flyover ramp located in the left lane that serves
through-traffic heading to Ashburn.
Westbound Route 625 was widened from four to six lanes. The
intersection also handles traffic flow to businesses near
the intersection that lost direct access to Route 28 as the
interchange was built.
The busy intersection is one of the biggest commercial areas
along the corridor, making it the most complicated area in
terms of acquiring right-of-way. The team needed to acquire
around 90 parcels to complete the intersection, but it focused
on adding the most critical parcels first to get construction
started.
|
|
|
The existing intersection
at Route 625 created some of the worst backups along
Route 28 as commuters (top left) turned on westbound
625 toward AOL's corporate park and neighboring Ashburn.
|
As one area of the intersection was being constructed, right-of-way
and utility work was being done simultaneously in other areas.
"That interchange began without one single piece of
right-of-way cleared or utility moved," Shaw said. "The
contractor was able to go in from day one and see where they
could get right of way first so they could start construction.
Then [Shirley] phased the work accordingly."
VDOT estimated that under a traditional design-bid-build
process, right-of-way and utility work would have taken 24
to 36 months before construction could begin. On that schedule,
construction would have been set to begin in summer 2005.
Instead, using the project's encompassing design-build method,
work on the interchange began in 2002 and it was open to traffic
by December 2004.
But meeting its schedule demanded firm commitment by all
parties, said Dave Mahoney, project manager at Dewberry &
Davis. The construction team and VDOT missed only one weekly
meeting during the first 26 months on the job and they worked
together on an almost daily basis to handle any hiccups, Mahoney
said.
VDOT has also kept its commitment to turn around plan reviews
within 15 days, Mahoney added.
"We haven't made many changes during construction because
everyone gave their input in a timely fashion during the design
process," he said. "The wheels could fall off this
thing at anytime if people start to lose their focus. This
is a multiyear project and it can be difficult to keep someone's
attention for that long, but we're all doing it the way it
should be done."
Multimillion dollar saving
The team faced its first big challenge at Route 625 near
the beginning of the job. Despite planning and budgeting for
utility relocation, the team discovered a 24-in. waterline
that it hadn't previously identified.
|
|
|
When the construction
team began work on the Route 625 interchange, it discovered
a 24-in. waterline that it hadn't previously identified.
VDOT's limited-access restrictions would normally require
that the waterline be moved completely out of the interchange
footprint. During a three-month period, VDOT relaxed
its access rules, Dewberry came up with a cost-effective
redesign and Shirley began building a 30-ft. retaining
wall that left 90 percent of the waterline in place.
|
VDOT's limited-access restrictions would normally require
that the waterline be moved completely out of the interchange
footprint, said Jon Harmon, development manager for Route
28 Corridor Improvements. During a three-month period, VDOT
relaxed its access rules, Dewberry came up with a cost-effective
redesign and Shirley began building a 30-ft. retaining wall
that left 90 percent of the waterline in place, Harmon said.
"Instead of a couple of million dollars in changes
that would have thrown a monkey wrench in the works from day
one, it was a no-cost win for everyone," he added. "It
really set the tone for the job."
The team faced another potential holdup as it worked on
plans to widen Route 625. The Washington & Old Dominion
Trail - a state-operated, multiuse, rails-to-trails path -
crosses Route 625 near the new interchange. Even as construction
was going on to open up the interchange, the team was working
with the Virginia Department of Historic Resources and other
state agencies to get the necessary approvals to change the
W&OD crossing.
"Normally, the whole project would have been held up
until all of that was settled," Mahoney said. "Instead
we were able to open the interchange on time and now there
are no longer 80,000 cars sitting at that intersection everyday."
Funding a Freeway
|