|
Double Time
Construction crew takes the express
route to double-tracking Baltimore's light rail system
By Jim Parsons
From residential backyards to the middle of nowhere, construction
teams are carefully navigating a path toward completion
of the $150 million 9.5-mi. light rail project in Baltimore.
|
|
|
The $150 million
project includes new 4-ft., 8.5-in.-gauge tracks on
more than 20,000 8-ft., 3-in. concrete ties, and 435
20- to 40-ft.-long steel catenary poles on poured concrete
foundations for the overhead high-voltage lines.
|
A deliberate, extended shutdown normally is not a good thing
for a public transit system serving more than 30,000 passengers
daily, but for the Maryland Transit Agency, idling large portions
of the Baltimore Light Rail system put a 9.5-mi. double-tracking
project on the fast track to completion.
Twin tracks were part of the overall vision for the 29-mi.
electrified system, which runs north-south from Hunt Valley
to Cromwell Station/Glen Burnie. Due to funding shortfalls,
approximately 40 percent of the system remained single track
when operations began in 1992. These segments, ranging in
length from just over 1,000 ft. to nearly 2 mi., were spread
across the system, limiting MTA's ability to expand service
and coordinate maintenance.
"For the most part, we had room for double tracks in
the right-of-way, and most of our 33 stations were built with
platforms on both sides," said Steve Silva, MTA's director
of engineering and construction. "What we lacked were
the rails themselves."
Cleared for completion
Funds from TEA-21 and the state provided the $150 million
MTA needed to begin filling its rail gaps in 2003. The project
includes new 4-ft., 8.5-in.-gauge tracks on more than 20,000
8-ft., 3-in. concrete ties, and 435 20- to 40-ft.-long steel
catenary poles on poured concrete foundations for the overhead
high-voltage lines. Eight track segments are included in the
project.
Only spurs to downtown Penn Station and Baltimore-Washington
International Airport, plus the extreme north end of the system,
will remain single track due to unfeasible geometrics and
right-of-way constraints.
Each of the eight segments presented a unique set of challenges.
While much of the right-of-way averages 66 ft. wide, the close
proximity of buildings, roads and terrain in some locations
left little room to work and stage equipment. Some segments
required relocating existing tracks, catenary poles and other
equipment from the middle of the right-of-way to make room
for a parallel rail line.
Dozens of underground utilities also had to be identified
and relocated. And, two major bridges would be needed to carry
the new tracks through the south end of Baltimore's Inner
Harbor.
"That meant preparing for a full range of work settings,
from residential backyards to what seemed like the middle
of nowhere," said project manager Ken Merrill of construction
manager PRW, a Baltimore-based joint venture of Parsons Brinckerhoff;
Rummel, Klepper & Kahl; and Wallace, Montgomery &
Associates. "That's on top of the safety considerations
of working within an active rail line."
Switching service
MTA was also concerned about how repeated service interruptions
would affect its customers, even with an aggressive public
outreach program of community meetings, fliers and dedicated
Web site.
"As we started to do more of the physical work, it
became apparent that the best way for the project to proceed
was to shut down one half of the system at a time," Silva
said. "This would allow the contractors to work more
efficiently and safely, limit repeated inconveniences to our
customers and eliminate the need for nighttime construction
in the neighborhood areas."
With MTA shuttle buses providing a temporarily substitute
for rail service, the shutdown began on the system's South
Line from Camden Yards to Cromwell in February 2004. Construction
workers made the most of the train-free environment, constructing
new tracks in four segments with seven grade crossings, two
new traction power substations and new signals and switches.
New 500-ft., cast-in-place platforms were built at three stations,
each with raised sections to accommodate disabled passengers.
One of the toughest locations was the system's junction
with a single-track spur to BWI.
"We had to install six switches, each with a complicated
conduit system, and two rail crossovers in a relatively small
area," Merrill said. "With very tight tolerances
and little room to make adjustments, we needed a lot of coordination
to make everything fit."
A new direction
|
|
|
Approximately
40 percent of the 29-mi. electrified system was single
track when operations began in 1992, but contractors
on the recent double-tracking project had enough room
build in most of the existing right-of-way.
|
The benefits of MTA's shutdown strategy proved better than
expected. With the South Line's double-tracking completed
more than four months ahead of schedule, full service resumed
in December.
Attention has now turned to the somewhat more complicated
North Line, which was shut down in January. Here, MTA shares
a portion of its right-of-way with an active freight line,
requiring double-tracking construction to be coordinated with
periodic deliveries of rail cars.
"Fortunately, it's only a few cars once a week, but
we still have to coordinate with the railroad to make sure
the tracks and switches are operational," Merrill said.
The North Line's upland terrain and close proximity to other
features such as Interstate 83 and parkland has presented
some additional civil engineering issues.
"During construction, the existing conduits were found
to be much closer to the steep western slopes than indicated
on the as-built plans," said MTA project manager Matt
Fenton. "That required additional excavation into the
slip plane of the slopes."
Four slope areas ranging from 90 to 250 ft. long required
further stabilization to minimize risk to the light rail line.
Two were stabilized with additional grading and landscaping.
Another area required a soldier-pile wall with concrete lagging,
while the fourth was fitted with a shotcrete wall anchored
with 10-ft. soil nails.
A good track record
|
|
|
A row of more
than 30 concrete piers stood parallel to the MTA Light
Rail System's .75-mi. crossing of Middle Branch in downtown
Baltimore for nearly 15 years. Built as part of the
original system, the piers were intended to provide
ready-made infrastructure for the day when funds for
double-tracking became available.
|
The double-tracking project has offered some glimpses into
the past.
"The North Line is one of the oldest railroad rights-of-way
in America with many historic structures," Fenton said.
"We've been careful when working near certain abutments
and a privately owned 19th Century station."
Workers also uncovered several marble rail ties from a long-ago
rail line. "We were not permitted to disturb them, so
we noted the location and reburied them in place," Merrill
said.
Silva said he is confident that the shutdown will duplicate
the South Line success with an early restart of service.
"Our schedule says 2006, but we're working toward a
partial reopening this summer and completion in December,"
he said, adding that MTA's passengers have generally accepted
the short-term inconveniences in exchange for long-term benefits.
Head Start
|