|
Transforming a Thoroughfare
State of Delaware combines roadwork
with recreation
By Sheila Bacon
The $130 million Blue Ball Properties project will revamp
U.S. Highway 202 and the surrounding area just north of
Wilmington.
|
|
|
A six-lane, 1-mi.-long
bypass road was constructed just west of U.S. 202 to
accommodate traffic routed off the existing highway.
Traffic was shifted in summer 2004 to the bypass so
crews could build two underpasses beneath U.S. 202,
a job currently underway.
|
The lion's share of the $130 million Blue Ball Properties
project involves improvements to U.S. Highway 202 and surrounding
roadways north of Wilmington, Del.
Nearly $110 million is dedicated to roadwork during the five-year,
multiphased project, which will bring new underpasses, streamlined
on- and off-ramps, improved lighting and wider roadways. Also
included will be 150 acres of surrounding park space, an expanded
golf course, new playfields and renovation of the property's
historic Blue Ball Dairy Farm barn.
The project is scheduled for completion in 2007. It was launched
by Delaware in 1999 after the state's successful bid to bring
the world's third-largest pharmaceutical company's U.S. headquarters
to Delaware's Brandywine Hundred area.
|
|
|
Among the area's
improvements is the renovation of the Blue Ball Dairy
Barn, just southwest of the intersection of U.S. 202
and Rockland Road. The barn was built in 1914 by Alfred
I. duPont as part of a farming operation that provided
food for area residents. The State of Delaware finalized
purchase of the barn in 2002 and it is being transformed
into a community center and administrative space for
the surrounding park's staff..
|
The merger of pharmaceutical manufacturing companies Astra
and Zeneca resulted in a doubling of Zeneca's existing 88-acre
campus at U.S. 202 and State Route 141. The venture seeks
to accommodate AstraZeneca's expanded operations while boosting
economic development and improving the overall area for the
surrounding community.
Work started in 2002 and thus far has included construction
of a two-acre wetland mitigation site, a regional stormwater
management system to address drainage issues and a six-lane,
1-mi.-long bypass road just west of U.S. 202 to accommodate
traffic routed off the existing highway. Traffic was shifted
in summer 2004 to the bypass so crews could build two underpasses
beneath U.S. 202, a job currently under way.
Considerable Communication
Seven separate utilities were relocated and consolidated
in a common utility tunnel before any roadwork began, creating
the need for considerable communication between all entities,
said project engineer Bruce Kay of Philadelphia engineering
consulting firm DMJM+HARRIS.
Water, electricity, gas, cable, phone lines and other utilities
were located above and below ground and on both sides of U.S.
202 before the reroute. The new tunnel carries the consolidated
utilities underground and parallel to the new bypass road.
The majority of the initial phase of work was completed by
general contractor Mumford and Miller of Dover, Del.
Shifting traffic from the busy highway to the bypass road
required months of coordination and the better part of a weekend
to execute, Kay said. The highway accommodates approximately
80,000 cars per day.
General contractor R.E. Pierson of Pilesgrove, N.J., was
joined by paving, lane painting, signalization and other subcontractors
during the complex shift, and crews finished the job well
before the Monday rush hour.
R.E. Pierson's subcontractor, Brubacher Excavating of Bowmansville,
Pa., recently completed blasting 10,000 cu. yds. of blue-gray
granite beneath U.S. 202 to make way for the two underpasses
at East Park Drive and Foulk Road/ SR 141 spur. Seismographs
were placed at the Blue Ball Dairy barn and nearby city water
reservoir to measure possible effects of the blasts, though
no damage was detected.
|
|
|
Shifting traffic
from U.S. 202 to the bypass road required months of
coordination and the better part of a weekend to execute.
General contractor R.E. Pierson was joined by paving,
lane painting, signalization and other subcontractors
during the complex shift, and crews finished the job
well before the Monday rush hour.
|
The underpass structures incorporate a considerable amount
of architectural stone retrieved from the blasting efforts,
said Ralph Farbaugh, R.E. Pierson's project manager. One outcome
of numerous community meetings indicated the desire to match
the design of the surrounding community's buildings, such
as those on the campus of Wilmington's Alfred I. duPont Hospital
for Children.
Upcoming phases of the Blue Ball Properties project include
reconfiguration of the new bypass road for use within the
new park, construction of a SR 141 spur near the AstraZeneca
campus, various improvements along U.S. 202 and reconstruction
of the Interstate 95/U.S. 202 interchange.
DelDOT's involvement in improvements that reach beyond road
widening and on-ramp construction is a new-but-deliberate
move for the transportation department that encourages design
and construction of projects that enhance communities, said
Mark Tudor, Blue Ball Properties project manager.
"We want to be able to think of all the issues that
make up major improvement projects and ask ourselves, 'What
else can we do so that the surrounding area is a better place
when we leave?'" Tudor said.
Blue Ball Properties Roadwork
Improves U.S. 202 and Surrounding Roadways
Keeping it Green
|