|
Penny Savvy, But Pound Foolish?
By Shawn R. Farrell
Signing a waiver of liens and claims may help you receive
partial payments in the short term, but could cost you more
later.
|
|
|
Shawn R. Farrell is a partner at the
law firm of Cohen, Seglias, Pallas, Greenhall &
Furman in Philadelphia, Pa., and concentrates his practice
in the area of construction law. He can be contacted
at (215) 564-1700.
|
Imagine you are a subcontractor who has experienced delays
to the timely performance of your work. You have submitted
numerous letters to the general contractor explaining the
delay, your intention to seek more money, and a request for
a time extension. But the owner has not yet agreed to pay
you any additional money or give you an extension. As you
wait for a response, the general contractor wants to give
you a partial payment for the work previous performed, however,
he demands that you sign a waiver of liens and claims. Do
you sign it?
Lien waivers, as their name implies, pertain to lien rights
and historically do not speak to the general right for payment.
While making periodic payments, the cautious prime contractor
may want protection against its subcontractor's failure to
flow money down to its employees, suppliers, lower-tiered
subcontractors and a host of other potentially troublesome
creditors of the subcontractor.
The general contractor may use this as justification for
the subcontractor to sign a waiver, but as the hypothetical
example suggests, things may not be as simple as they seem.
The problem arises when the subcontractor is owed additional
money and the owner or general contractor disagrees.
By signing a waiver of liens and claims, the subcontractor
may lose its right for additional money. In fact, a recent
federal court case held just that. In the case, a drywall
subcontractor was asked to perform additional work after the
project had been delayed for one year. As required by the
contract, the drywall subcontractor signed waivers, in order
to receive partial payment for the additional work. In addition,
the drywall subcontractor sent periodic letters explaining
that the change orders did not include all the costs that
arose from the delay and additional money was owed which was
impossible to quantify until the end of the project. At the
end of the project, the drywall subcontractor sued the general
contractor, seeking delay damages.
Astonishingly, the court found that the drywall subcontractor
waived any claim for additional monies by signing the waivers.
The fact that it sent letters to the general contractor notifying
it of the additional money claimed was immaterial. What the
drywall subcontractor had waived could not be recaptured through
a letter.
So what is a contractor to do? If you do not sign the waiver
of liens and claims, you do not receive the partial payments.
If you sign the waiver of liens and claims, you may not be
able to pursue any additional claim for money at the end of
the project.
One suggestion is to strike from your contract any obligation
to sign a waiver of liens and claims as a condition precedent
to the receipt of a partial payment.
If this can't be done or if it's too late to do so, strike
from the waiver itself any reference to "claims for any
contract balance or credits owed for any labor or material
provided pursuant to the subcontract work." Initial these
strikeouts along with signing the waiver.
If neither of these steps is possible, send a letter with
the waiver that clearly states that you do not release or
waive any claim for additional consideration arising out of
delay, acceleration or pending change orders.
Finally, comply with all notice requirements in the contract
and state, in writing, that pursuant to the terms of the contract,
you are putting the contractor on notice of a claim for additional
money. If possible, state the amount of the claim.
While you may need the partial payment to meet your payroll
obligations and pay your suppliers, there can be negative
ramifications from signing a waiver of liens and claims. When
you sign such a document, you are altering the terms and conditions
of your contract. Make sure that waiver says exactly what
you and the general contractor have agreed upon. Failure to
take this simple step may prevent you from getting paid for
all the work you performed.
|