|
Airport - Award of Merit
Dulles Airport Runway 12-30
Dulles, Va.
Faced
with a breakneck schedule and numerous obstacles, The Lane
Construction Corp. finished the $17 million reconstruction
of Dulles International Airport's only east-west runway in
an incredibly short time frame - with 13 days to spare.
The existing runway needed repair. Numerous concrete panels
were cracked and the existing PCC pavement section was underdesigned
for the industry's new, larger aircraft. An inadequate underdrain
system caused large volumes of water to collect in the existing
subgrade below the runway.
Crews installed 24,000 lin. ft. of underdrain systems; demolished
185,000 sq. yds. of PCC pavement, base material and subgrade;
and installed several duct-bank and pipe-casing crossings.
Work continued with the cement stabilization of 175,000 sq.
yds. of subgrade 12-in. deep, placement of 185,000 sq. yds.
of asphalt base and installation of several hundred runway
and touchdown lights.
Meeting or exceeding the 134-day schedule was critical for
the Metropolitan Washington Airports Authority, the project's
owner. Runway 12-30 is the only east-west runway that is used
during heavy hurricane season, when the airport is especially
susceptible to high winds - and hurricane season was fast
approaching.
If the runway was inoperable during a high crosswind period,
the airport could be shut down until the adverse weather subsided.
The region's concrete shortage threatened to stall the project
before it even started. Lane's cement supplier rescinded its
material quote one month after the notice to proceed. Lane
had to scramble to obtain a supplier that could provide 27,000
tons of cement and 4,000 tons of fly ash in a six- to eight-week
time period.
Lane recruited the help of MWAA and key members of the American
Concrete Paving Association to help fulfill the critical need.
Unlike many cementitious materials, granulated slag was readily
available, so Lane designed a concrete mix utilizing a 50/50
cement/slag blend that cut the initial concrete requirement
in half.
Lane crews were also able to free up more needed concrete
by switching from a cement-based material required directly
beneath the runway pavement to an asphalt-based material.
This freed up 4,000 tons of cement for the main runway PCC
pavement.
The cement stabilization of the subgrade soils was more
difficult than normal due to existing rocky soils, variable
soil types and wet subgrade. Hidden boulders in the 12-in.-deep
stabilization section damaged Lane's equipment - a reclaimer
- used to mix the cement and soil.
Additional equipment was mobilized to rake the subgrade and
remove boulders that could further damage the reclaimer.
The designer instituted the manipulation of subgrade soils
prior to the cement treatment with a lime treatment in saturated
areas and clay-rich areas where characteristics of the soil
could not be improved. This change allowed Lane to avoid undercutting
a significant amount of subgrade, saving considerable time
on the schedule.
"This project is emblematic of an industry with the
capacity to do outrageous things," said one judge. "It's
a large-scale project with a lot of concrete that was poured
in a short time frame - very difficult. They had an amazingly
short schedule, which was a big issue, considering the shortages
in concrete in our region."
Owner: Metropolitan Washington Airports
Authority
Design & Construction: Lane Construction Corp.
Electrical: Midasco Inc.
Saw & Seal: Jami & Co Sawing and Sealing
Soil Cement Stablization: Slurry Pavers Inc
Pavement Markings: Sellers Construction Corporation
Furnish & Haul Concrete: L&L Construction & Associates
Runway Grooving: Saftey Grinding & Grooving
Return to Categories List
|