|
Bridge - Award of Merit
Atlantic Intracoastal Waterway Bridge
Great Bridge, Va.
The
new Atlantic Intracoastal Waterway Bridge at Great Bridge,
Va., is the latest in a series of structures that dates back
to a 40-yd. span across what was once the southern branch
of the Elizabeth River in the 1770s.
Even with the advantages of 21st Century engineering techniques,
however, the 300- ft.-long five-lane, hydraulically driven,
double-leaf bascule bridge represents a design and construction
effort truly befitting of its namesake community.
Consider the constraints. Erecting a replacement to the existing
two-lane double-span swing bridge could not disrupt the flow
of either vessels or vehicles. The U.S. Coast Guard allowed
only four 72-hour channel closures during the 800-day construction
period, each of which had to be scheduled to the precise hour
90 days in advance.
Landside construction would take place within the confines
of a busy commercial area. And because the site had also been
the setting of significant American Revolution and Civil War
battles, the project team had to continually watch for potentially
significant artifacts.
Overcoming these and other obstacles made teamwork essential
among the project's co-owners, engineer and contractor. For
example, the bridge's original design called for the bridge
leaves to be operated by 1,500-ton hydraulic overhead counterweights
to provide a low-level profile and avoid the need for deep
cofferdams.
To expedite construction, the engineer, URS Corp., of Virginia
Beach, Va., and the contractor Tidewater Skanska Inc. of Norfolk,
Va., elected to make several design adjustments to split the
structural connections and erect the counterweights shored
in the closed position.
The 270-ton, 140-ft. leaf portions were preassembled offsite
and floated into place during two of the channel closings.
Roadway decks and the final sections of counterweights were
built during two approved channel closures.
Maintaining a pinpoint schedule was not the only ongoing
challenge. Beneath the cofferdams lay soil and groundwater
with higher-than-expected concentrations of lead and hydrocarbons.
An innovative dewatering system diverted and separated incoming
channel water from the contaminated groundwater, thereby reducing
the amount of water requiring treatment.
The project team's commitment to collaboration paid off in
both precision and productivity. Each of the four 42-ton track
girders was set to .03-in. tolerance for horizontal and vertical
alignment, with a level tolerance of .006 in. per foot. When
the leaves were closed and mated for the first time, they
were within 1/8 in. of the 110-ft. plan length, and leaf alignment
was within .5 in. of specification.
"The success of this project is a credit to all the
team members," the judges said. "That fact that
they were able to keep two lanes of traffic open was amazing.
And they did it three months ahead of schedule with no lost-time
injuries."
Along with giving Virginia its first fully hydraulic bridge,
the project also revealed a long-hidden part of its past.
During excavation work for the bridge approaches, the project
team uncovered portions of an old cypress timber roadway laid
by the British Army in 1776. The relics were turned over to
the local historical society, which plans to build a museum
adjacent to the area's newest "great" bridge.
Owner: U.S. Army Corps of Engineers
Co-Owner: City of Chesapeake
Design Engineer: URS Corporation
Prime Contractor: "Tidewater Skanska, Inc."
Hydraulic Equipment: Supply Bosch Rexroth
Structural Steel Fabricator: PDM Bridge
Hydraulic Fluid Power Systems Installation/Bridge Controls:
Electro Hydraulic Machinery Co.
Soil Anchors: Foundation Services/Hayward Baker
Electical and Controls: "J.C. Driskill, Inc."
HVAC/Mechanical: Smith & Keene
Sitework: "Womack Contractors, Inc."
Return to List
|