|
Cultural Institution- Project of
the Year
National Air and Space Museum Steven
F. Udvar-Hazy Center
Chantilly, Va.
The
National Air and Space Museum's Steven F. Udvar-Hazy Center
at Washington Dulles International Airport allows the Smithsonian
Institution to showcase more of its vast collection and tell
the story of aviation and space exploration in a hanger-style
setting.
Smithsonian officials had longed to build an aviation museum
near the Chantilly, Va., airport, but the project remained
a dream until Steven F. Udvar-Hazy, International Lease Finance
Corp. of Los Angeles chairman and CEO, donated $65 million.
Hensel Phelps Construction Co. of Chantilly began construction
in April 2001, after receiving the $156 million contract to
construct the 615,000-sq.-ft. museum through a best-value
procurement method.
Hellmuth, Obata + Kassabaum of St. Louis designed the facility.
When additional funds are raised, the project will include
a second phase with a restoration hanger and storage facilities.
Hensel Phelps offered the owner $5.9 million in value-engineering
ideas, of which $2.1 million were selected. The company donated
100 percent of its shared savings back to the Smithsonian.
The exhibition space is 10 stories high and the length of
three football fields. Planes are suspended from 21 steel,
arched trusses. Two elevated overlooks enable visitors to
study suspended planes from above as well as at ground level.
Hensel Phelps completed the project in time for a grand opening
on Dec. 15, 2003, the 100th anniversary of the Wright brothers'
notorious first flight. The construction firm remained onsite
through April.
The museum's 176.5-acre parcel sits just south of the main
terminal at Dulles Airport. The facility has access to an
active runway so planes can fly in and taxi directly to the
museum.
Such close proximity to a functioning airport required close
cooperation and partnering with the Commonwealth of Virginia,
the Metropolitan Washington Airport Authority, the Virginia
Department of Transportation and the site contractor, New
Construction of Vienna, Va.
Hensel Phelps created a separate construction entrance, and
no disruptions of airport activities occurred during museum
construction.
Hensel Phelps self-performed the earthwork, concrete and rough
and finish carpentry. Seventy-four subcontractors worked on
the project.
About 415 workers were onsite at peak periods. All together,
about 1,500 craftspeople contributed to the project. Hensel
Phelps held numerous barbeques and team events to help motivate
workers and thank them for a job well done.
Assembling
the main hanger and erecting the 100-ton, steel, triangulated
trusses that support the roof and bear the weight of the display
aircraft presented the most challenging aspect of the project.
The trusses, spaced 50 ft. apart, are 17 ft. wide at the base,
345 ft. long and span 230 ft. They are anchored to concrete
thrust blocks.
Each truss can support more than 22,000 lbs. or six aircraft
with a combined weight of 14,000 lbs. The original design
called for welding the three sections of each truss together,
but Hensel Phelps proposed using bolts instead. The bolts
sped the time of erection, saved the owner about $370,000
and ensured the quality of the connections. Crews lifted the
first truss into place at the end of January 2002.
A Hypalon single-ply roofing system that resists chemicals,
exhaust and oil covers the hangar. It was selected because
of the museum's closeness to airport takeoffs and landings.
The balance of the building has an aluminum roof.
The project included constructing a screening pit and seating
tiers for the 479-seat IMAX theater, erecting steel for the
164-ft.-tall observation tower and adding components to a
central utility plant.
During the final 12 months, work focused on completing the
interior and installing of 82 invaluable aircraft. Many of
the airplanes and space artifacts required reassembly in the
hanger and positioning either on the ground or suspended from
the trusses.
Crews began putting the Enola Gay, used to bomb Hiroshima
during World War II, together about four months before construction
of the entire museum wrapped up. It sits on the ground. Each
of the suspended aircraft are positioned in their typical
flight positions, with an aerobatic airplane upside down.
Hensel Phelps created a formal partnering program to ensure
commitment of all vested parties from the start. The project
team worked together to overcome obstacles and find solutions
to problems as they cropped up.
The Smithsonian and Hensel Phelps considered quality of workmanship
a top priority. The contractor, construction manager Parsons
Brinckerhoff of New York and an architect from HOK conducted
weekly job walks to assess the quality.
Concerned about safety, Hensel Phelps instituted a comprehensive
safety program for itself and subcontractors. Before starting
any new activity, the company held preparatory meetings to
review quality and safety requirements. It also performed
job hazard analyses. The company succeeded in keeping the
jobwide incident rate at 8.8 percent.
"This was a tough job," said one of the judges.
"The goals were well defined and the team stepped up
to the plate and performed."
Owner: Smithsonian Institution's
National Air and Space Museum
Architect: "Hellmuth, Obata
+ Kassabaum"
General Contractor: Hensel Phelps
Construction Co.
Architectural Woodwork: "Brunswick
Woodworking Co., Inc."
Masonry: "Calvert Masonry,
Inc."
"HVAC, Mechanical, Plumbing":
"John J Kirlin, Inc."
Steel Space Frame System: "MERO
Structures, Inc."
Landscaping: Valley Crest
Composite Tile-Faced Panel System:
"Wyatt, Inc."
Drilled Concrete Piers: Dominion
Casisson
Return to Categories List
|