|
Environmental - Award of Merit
Woodrow Wilson Bridge-Northwest
Branch/Sligo Creek Stream Mitigation
Oxon Hill, Md.
Teamwork
and innovation defined the Northwest Branch/Sligo Creek Stream
Mitigation project, which restored these channels to their
natural design to encourage the passage of fish.
The project was one part of a comprehensive environmental
mitigation project developed to compensate for environmental
impacts associated with the $2.4 billion construction of the
new Woodrow Wilson Bridge over the Potomac River.
Northwest Branch and Sligo Creek are tributaries of the Anacosita
River - which drains to the Potomac River in Washington, D.C.
- and are located in highly developed, urban areas. Human
influence over the years has caused blockages and barriers
in the tributaries that affect natural fish passage and spawning
habits.
Twelve existing stream blockages - eight in the Northwest
Branch and four in Sligo Creek - were targeted for re-establishment.
A high percentage of impervious surfaces in surrounding areas
had resulted in significant stream channelization, causing
once-meandering streams to form relatively straight flood-conveyance
channels.
Sewer lines that were once buried below the stream bottom
had become exposed as streams deepened and widened to accommodate
increased stormwater flow. These sewer and other utility lines
were the main source of fish migration blockages.
Additionally, grade-control structures installed in the 1960s
and 1970s had created hydraulic drops that fish could not
traverse.
Potomac Crossing Consultants and other project team members
utilized in-stream structures to facilitate fish passage over
the blockages. One type - the riffle-grade control structure
- is an engineered application designed to allow fish passage.
Compared to a traditional fish ladder, the RGC is designed
to mimic natural stream riffles and allow for a more natural
passage of the fish upstream to spawn.
This project was the first that used RGCs for the purpose
of fish passage.
"The project was stunning in its straightforward success,"
one of the judges said. "It was a difficult reclamation
and a creative solution."
Teamwork was important. A stream specialist and resident
engineer from Potomac Crossing Consultants joined the contractor's
design specialist onsite during construction, and the group
held weekly progress meetings to document and solve problems
as well as maintain open communication among all project stakeholders.
The design specialist was given the authority to approve
design changes on the spot, saving time and money and avoiding
delays associated with changing field conditions.
The Maryland Department of the Environment and the U.S Army
Corps of Engineers also helped the project run smoothly by
allowing the team to complete a limited amount of work "in
the wet." While stream diversions were used to conduct
work within a dry work area, the completed structures would
often need to be tweaked to accommodate fish passage design
parameters after the diversions had been removed.
The agencies allowed crews to shift boulders and riffle-grade
material without diverting the stream to maximize the potential
for fish passage.
The agencies also allowed limited work during the fish migration
season - typically off-limits for construction activity. Because
of this variance, the project team was able to ensure that
the new habitat would be open to migratory fish by the following
spring's spawning season.
Owner: Maryland State Highway
Adminstration
Design: KCI Technologies Inc.
Construction Management: Potomac
Crossing Consultants
Prime Contractor: Environmental
Quality Resources
Return to Categories List
|