|
High-Rise Residential - Project of
the Year
1210 Massachusetts Ave.
Washington, D.C.
The
JBG Co.'s new 233,000-sq.-ft. 1210 Massachusetts Ave., luxury
apartment building is part of the vanguard of downtown Washington's
residential revitalization.
Also known as Sovereign Park, the 13-story, 144-unit building
could not offer a better location to attract the growing number
of young professionals who are rediscovering urban living.
The famed nightlife hubs of Dupont Circle and Adams Morgan
are just blocks away, as are key District of Columbia employment
centers such as Capitol Hill, the new Washington Convention
Center and the K Street corridor.
The building also provides its tenants with a variety of
floor plans ranging from studios to one- and two-bedroom units,
plus a small number of two-level duplex models. A collection
of high-end units located on the tower's top two floors complements
the stunning views of the Nation's Capital.
The ground floor also features 750 sq. ft. of retail space
to further integrate the building into the community.
Unfortunately, convenience was in short supply for the project
team, which needed to transform what was an empty parking
lot and dilapidated buildings into this new landmark of luxury
living. Because of the irregular shape of the one-half acre
site, 1210 Massachusetts Ave. is essentially two separate
structures overlapping at a central connection.
Along with the typical challenges and constraints that accompany
working in a densely developed urban environment, general
contractor Tompkins Builders of Washington, D.C. had to rely
on only 80 ft. of frontage along L Street as the primary access
point into the site. A slightly larger secondary frontage
along Massachusetts Avenue could be used only sparingly because
of the high volume of traffic along the roadway.
With three existing structures bordering the site, extensive
underpinning was necessary during the excavation of more than
35,000 cu. yds. of rocky soil.
As
Tompkins dug 40 ft. below the surface to install the spread
footings and partial mat foundation for the apartment building's
four-level parking garage, special attention had to be given
to protecting an overhanging fire escape that served the historic
Swiss Inn Hotel next door. To preserve a safe evacuation route
in the event of a fire, Tompkins' workers attached the fire
escape to the protective underpinning.
Once construction reached street level, the project team
scrapped the Swiss Inn's old fire escape in favor of a more
modern replacement.
"To build anything on this site is amazing," said
one judge, who added that the unusual skin for apartment building
"made the process even tougher."
Indeed, the exterior of the building's reinforced structural
concrete frame adds texture literally and figuratively to
its urban surroundings. WDG Architecture of Washington, D.C.
incorporated a variety of bay windows, terraces and setbacks
into the skin, resulting in 23 different vertical faces.
The skin also included a variety of materials that included
limestone, brick, synthetic stucco and precast concrete. Because
the materials were scattered across the building's skin, application
and finishing had to be carefully coordinated with other construction
activities.
An unexpected challenge arose during construction when citywide
concerns about building waterproofing led JBG to request additional
measures to safeguard the building from the potential of water
intrusion. Along with eliminating fireplaces except for the
upper-level units, the project team had to make substantial
modifications to the already complex building skin.
The project team's research led to the selection of a new
elastometic membrane manufactured by Sto Corp. of Atlanta
behind the skin. Other waterproofing measures included encasing
all mechanical and electrical penetrations in sleeves and
upgrading the flashing details around windows, doorways and
other surface features.
Tompkins site-specific quality-control plan, inspection
programs and ongoing communication among the various subcontractors
proved essential in helping the team implement the changes
without disrupting what was already a demanding project schedule.
The building was completed in mid-July after 18 months of
construction - more than a month ahead of the original contract
completion date.
The complex project also had no lost-time accidents thanks
to an innovative approach to safety. The project's safety
committee included a Tompkins superintendent and designated
nonsupervisory craftworkers from each trade, eliminating the
"politics" sometimes involved in such oversight
efforts.
Weekly meetings that included jobsite inspections complemented
the spirit of open exchange between Tompkins and craftworkers.
Superior safety performance was also rewarded with monthly
awards and other incentives.
Owner: JBG Companies
Architect: WDG Architecture
Construction Manager/General Contractor:
"Tompkins Builders, Inc."
Shoring & Underpinning Contractor:
"Steele Foundations, Inc."
Structural Concrete Contractor: Miller
& Long
Electrical Contractor: The Limbach
Group
Masonry Contractor: Spartan
Masonry
Drywall Contractor: P&P
Contractors
Return to Categories List
|