|
Highway - Award of Merit
Pentagon-Remote Delivery Facility
- Secure Access Lane
Alexandria, Va.
Sensitive
and fluctuating security requirements required flexibility
by the project team that had the task of improving safety
at the grounds of the Pentagon Reservation.
Despite numerous job-scope changes, design-build partners
Shirley Contracting Co. of Lorton, Va., and Earth Tech of
Alexandria, Va., still brought the Remote Delivery Facility-Secure
Access Lane to completion on time and $1.4 million under budget.
The RDF-SAL was a fast-track, design-build project completed
in 14 months as part of the Pentagon Renovation Program. Its
purpose was to enhance existing security at the Pentagon by
means of roadway access configuration - to increase standoff
distance from the Pentagon - and the installation of security
and access control devices.
To minimize disruption to existing traffic, pedestrian access
and Pentagon functions, construction of the project was divided
into three phases. First, crews reconfigured the Washington
Boulevard/Columbia Pike interchange, demolishing three existing
ramps and building three new ramps in a different configuration.
Phase two involved construction of new truck queue/security
stations as well as a new secure access lane to tie the truck
queue to the RDF. This phase included installation of vehicle
barriers with 15,000-lbs.-at-50-miles-per-hour rating, bullet
resistant-rated guard booths, CCTV cameras, full communication
and computer capabilities, and a public address system.
Construction of a blast-wall system defined the third phase.
The system - built alongside the Secure Access Lane - included
a 20-ft.-high wall with a 50-ft.-wide earth embankment.
The design-build team was faced with ever-changing security
requirements, along with designs passed down from the Department
of Defense and the Pentagon Force Protection Agency. On several
occasions, new requirements were presented after the final
design was reviewed and approved.
Contractors and designers had to quickly and efficiently
revise the plans to incorporate the new requests without disrupting
any of the completed or future construction elements. A major
change came when two new security stations were added in the
truck queue area to house inspection guards and the K-9 units.
The original plans housed both of these units inside the
RDF, but new requirements placed them in the truck queue so
all vehicles could be inspected by guards and specially trained
dogs before entering the facility.
All new requirements were met without creating any major
construction, schedule or budget problems.
The locations of existing utilities also posed a problem.
Initial plans did not indicate several of the utilities, and
the location of many conflicted with construction plans for
the SAL and blast wall. Utility relocation and protection
plans were quickly devised, implementing new and innovative
ideas to protect and reinforce underground systems.
The project required the team's close coordination with
numerous agencies, including the Virginia Department of Transportation,
Arlington County, the Pentagon Force Protection Agency, the
Defense Facilities Directorate, the National Capital Planning
Commission and the Commission of Fine Arts.
"This was an outstanding effort by the team,"
said one of the judges. "The project was intensely partnered
and involved intense security issues."
Owner: Pentagon Renovation
& Construction Program
General Contractor: Shirley
Contracting Co.
Design Team: Earth Tech
Weidlinger Associates
CTI Consultants
Concrete Contractor: Tavares
Concrete
Electrical & Lighting Contractor:
"R.E. Lee Electric Co., Inc"
Landscaping: Chapel Valley
Landscaping
Return to Categories List
|