|
Best of 2004 Project of the Year
National Institute of Standards and
Technology - Advanced Measurement Laboratory
Gaithersburg, Md.
When
the National Institute of Standards and Technology sought
to create its new Advanced Measurement Laboratory, its vision
left no room for error. After nearly ten years of design and
36 months of construction, HDR and Clark/Gilford carried out
the mission to perfection and earned Mid-Atlantic
Construction's Project of the Year award.
Perfection is a goal that many architects and contractors
aim for in their projects, but in the case of the National
Institute of Standards and Technology's Advanced Measurement
Laboratory project, perfection wasn't merely an aspiration,
it was an expectation.
For more than 100 years, NIST has developed the measurements
and standards necessary for the United States to be a leader
in technology. With the creation of the $184 million Advanced
Measurement Laboratory in Gaithersburg, Md., NIST looked to
further hone its ability to conduct sophisticated measurements
and be more globally competitive.
Creating a facility that allows scientists to successfully
work at subatomic and nano levels required progressive architectural
designs, well-planned schedules and careful coordination among
the various team members.
By achieving its lofty goals on time and on budget, the
project caught the attention of Mid-Atlantic
Construction's Best of 2004 awards program jury and
earned it the title of Project of the Year.
"The construction effort on this project is phenomenal,"
one judge said. "I've never seen a job like this. It's
more complicated than anyone will ever see or know because
it is a clean-room facility. Everything had to be sterilized
onsite - the tools, the people - everything. It took teamwork
and intense coordination to get it done."
The 536,500-sq.-ft. facility houses hundreds of labs in
its five wings with varied and sometimes conflicting purposes.
The AML includes 187 instrument lab modules and 151 metrology
lab modules.
Specialty
areas within the AML include 12 precision temperature-control
labs that are accurate up to .01 degree Celsius; 36 precision
temperature-control labs that are accurate up to .1 degree
Celsius; 27 extremely low-vibration laboratories; several
labs with humidity fluctuations of no more than 1 percent;
and a 33,000-sq.-ft. clean-room facility that is Class 100,
upgradeable to Class 10.
Achieving that level of precision created a daunting challenge
for Alexandria, Va.-based architect and engineer HDR.
"When researchers first told us they wanted spaces
designed within this building with temperatures so tightly
controlled that they couldn't fluctuate more than 1/100th
of a degree Celsius, we thought it was a typo," said
Ahmad Soueid, principal and senior vice president at HDR.
Meeting those demands would require extensive mechanical
and electrical systems. Ultimately, the contract included
a nearly $56 million mechanical package and a $22 million
electrical package. One hundred and thirty-five custom air-handling
units and nearly 2.3 million lbs. of ductwork were needed
to keep airflow high enough to maintain temperature, humidity
and air quality controls.
The 12 precision temperature-control rooms would require
300 air changes per hour, while the clean-room facility called
for 600 air changes per hour.
In
addition to meeting those demands, HDR had to find ways to
make all of these systems co-exist without interfering with
each other. Very high levels of air exchange can cause mechanical
vibration and acoustical noise. Liquid cooling systems can
induce vibration, while heating systems can create electromagnetic
fields.
"Managing expectations of the owner, looking at the
conflicting requirements and coming up with a solution that
would give them what they need, that was the biggest challenge
of all," Soueid said.
HDR and NIST scientists worked for nearly 10 years, starting
in 1993, to find solutions. The team conducted multiple experiments
and built mock-up lab modules to test the accuracy of its
designs. Manufacturers were brought in to prove that they
could achieve the precise temperature controls inside the
mock-up lab modules.
HDR also developed innovative design concepts, including
extremely low-vibration labs that are built on top of deep
pits in the ground and lifted by a system of air springs to
reduce ambient vibration.
While its designs were advanced, HDR tried to simplify the
design wherever possible. The design called for mostly common
materials, including the air-spring system, which is modeled
after similar systems used in large trucks.
"If you look at the building itself, it's not that
sophisticated," Soueid said. "It's very intricate,
but it's made out of components that are readily available."
By 1996, a design was well under way, but Congress pulled
back funding and progress was stalled on the project until
2000. When the project began to move forward again, a joint
venture between Bethesda, Md.-based Clark Construction Group
and Beltsville, Md.-based Gilford Corp. was awarded the contract
to serve as general contractor. Gilford served as a 10 percent
partner in the deal.
Years of design gave way to months of planning and careful
coordination between the various team members to complete
the project within a tight 36-month time frame. While work
was under way on the high-precision labs, significant amounts
of mechanical and electrical systems needed to be installed
in a carefully coordinated and timely fashion.
"We had to build this job with the mindset of what
we needed to do to get the mechanical systems and electrical
systems online as soon as possible," said Joe Hogan,
project manager for Clark Construction. "The structure
and finishes became secondary."
Hogan said the team worked to quickly establish the interstitial
spaces, which housed the mechanical and electrical systems,
above the lab modules so that work could go on in both spaces
simultaneously. In some cases, the team used temporary support
of walls before pouring the roof structure on the underground
metrology buildings to help get other facets of the work done
early.
The project's mechanical subcontractor, John J Kirlin of
Rockville, Md., also found ways to save time. Sections of
ductwork, up to 30 ft. long, were prefabricated offsite by
Stromberg Metal Works of Beltsville, Md., brought to the location
and put in place. Likewise, large sections of piping were
also preassembled before being installed.
"Part of the uniqueness of this job was that it forced
us as contractors to think outside the box in how to build
it," Hogan said.
Meanwhile,
building out the lab modules required significant precision.
Metal skin panels overlaying 4-in.-thick phenolic insulation
had to be installed perfectly to prevent air leakage and preserve
temperature controls. No metal could penetrate the lab modules
from the panels because that could also compromise thermal
control.
Clean rooms were built in a clean environment from the onset.
The further into the process of constructing the clean room,
the more stringent the cleanliness became. As the labs were
completed, craftsmen wore body suits and all of their tools
had to be wiped sanitary clean to work in the space.
"It has to be a concept of building clean in order
to get the certification," Hogan said.
Despite careful planning and execution, design changes did
have to be made because of budgetary concerns and in response
to input from NIST scientists. Despite the time constraints
and changes, the project finished on schedule. During testing
of the facilities, the labs successfully achieved their stringent
requirements, in many cases exceeding them.
It was a relief to Hogan and his crew.
"The mock-ups preformed well, but it was still an unknown
whether it would work or not because it was not the exact
same design layout," Hogan said. "As it turns out,
it was a tremendous success, but as we were building it, it
was an unknown."
But Chris Conley, project manager and contracting officer's
technical representative for NIST, said he was confident everything
would come together.
"We knew we'd get it right," he added. "We
had a good team on this job from the government standpoint
and the A&E firm and the construction people."
Owner: NIST
Architect/Engineer: "HDR,
Inc."
General Contractor": Clark/Gilford
a Joint Venture
Mechanical Contractor: John
J Kirlin
Electrical Contractor: Singleton
Electric
Concrete Contractor: Clark
Concrete Co.
Drywall Contractor: "C.J.
Coakley Co., Inc."
Structural Steel Contractor:
Globe Iron
Curtainwall Contractor: PCC
Inc.
Click her for the Institutional-Award
of Merit
Return to Categories List
|