|
Institutional - Award of Merit
University of Maryland Health
Center
College Park, Md.
Forrester
Construction Co. of Rockville, Md., completed a $4.8 million
addition to the University of Maryland Health Center while
students continued to receive care.
"This was a tough site - patients and staff during
construction occupied the building," said one of the
judges. "It was very hard to build in this location with
the logistics. This project is definitely a winner."
The original health center, built in 1963, needed a major
upgrade to meet modern health-care standards and improve care
delivery and traffic flow. About 350 students receive treatment
at the center each day, totaling approximately 60,000 medical
visits annually. Students frequently waited in long lines
in the hallways.
Forrester received a $7 million construction-manager-at-risk
contract in 2001 to add 25,000 sq. ft. to the center, doubling
its size. Anshen+Allen of Baltimore designed the expansion.
Funding problems delayed the start of work until fall of
2002. Construction of the first phase, the expansion, wrapped
up in January 2004 and crews began renovating the existing
space. Forrester completed the job two months ahead of schedule.
The concrete addition wrapped around the east side of the
former health center. At each floor, punch-through openings,
18 ft. wide and 12 ft. tall, connected the existing and new
sections. Crews shored the slabs with structural steel and
removed the existing exterior wall sections by hand while
students received medical treatment behind temporary partitions
just a few feet away.
During the first day of footer excavations, Forrester found
that the existing building's footer was higher than expected
and any work on the new structure could undermine the occupied
health center. Forrester solved the problem by lowering column
footings and adding new reinforcing steel, and it shifted
to work along the perimeter until the underpinning was complete.
Adjacent buildings, parking and a road locked in the construction
site on all four sides, requiring the use of multiple mobile
cranes working inside the building footprint, rather than
a tower crane as originally planned. Staging of materials
took place offsite.
Cold weather hampered the schedule, delaying excavation
and opening of the new south entrance. Concrete work progressed
despite the cold. But an unexpected steam leak delayed pours
until the university brought someone in to cap it.
Forrester tied into campus utilities at several adjacent
buildings and to underground mains. Crews added a chilled-water
loop, a high-pressure steam loop, stormwater and potable water
mains, an emergency generator duct bank and asphalt during
spring break to avoid disruptions.
Feeding the high-voltage electrical service from the existing
building into the new structure required close coordination
with the user. Heller Electric Co. of Brandywine, Md., completed
the electrical work.
The exterior brick masonry, performed by George Moehrle
Masonry of Frederick, Md., received recognition from the Washington
Building Congress Craftsmanship Awards program. The association
praised the Flemish bond, quoin and other detail work.
New features include a triage and waiting area; a physical
therapy unit; 35 patient examination rooms, up from 21; dental
chairs and additional lavatories; an elevator; and a larger
laboratory.
Owner: University of Maryland
Architect: Anshen + Allen
General Contractor: Forrester
Construction
Demolition: "Tammal Enterprises,
Inc."
Excavation: "Grade A Excavating
Co., Inc."
Site Work: "Chamberlain
Contractors, Inc."
Plumbing: Magnolia Plumbing
Environmental: LVI Environmental
Services Inc
Concrete: V & V Construction
Structural Concrete: AJO Concrete
Construction Inc
Masonry: "George Moehrle
Masonry, Inc"
Structural Steel: Inka Erection
Corporation
Electrical: Heller Electric
Company
Security: "Tech, Inc."
Click here for the
Institutional-Project of the Year
Return to Categories List
|