|
Office - Award of Merit
Fannie Mae Data Center
Urbana, Md.
Conquering
numerous obstacles, Holder Construction Co. of Reston, Va.,
completed the $102 million Fannie Mae Data Center in Urbana,
Md., within one year of breaking ground.
"To bring in $100 million in construction in under
[the goal of] 13 months is an amazing feat," said one
of the judges. "It was a very difficult project."
The complex 250,000-sq.-ft. facility includes a precast
concrete, 60-watts-per-sq.-ft. data center that connects with
a four-story, structural steel office building. Gensler
Architecture, Design &
Planning Worldwide of New York designed the data center
so Fannie Mae could increase its size to 125 watts per sq.
ft. to accommodate future growth.
A disaster recovery center in the basement serves this facility
and the Fannie Mae headquarters in Washington, D.C.
The project represented Fannie Mae's first use of a construction-manager-at-risk
contract, which resulted in significant changes to the processes
and procedures it had relied on for past projects.
Holder put together a team that exceeded the 6 percent minimum
minority- and women-owned business goal set by Fannie Mae.
The company contracted more than 17 percent of the trade work
to minority and women firms.
Holder broke ground in November 2003 and stayed on track
to complete the center one year later. Commissioning of the
data center began in September.
Crews worked around the clock, through harsh winter conditions,
on site preparation and foundation work. Francis O. Day Co.
Inc. of Rockville, Md., handled the site development.
The data center is located on a 37.5-acre green-field site
in an undeveloped industrial area about one-quarter mile from
existing utilities. The team worked closely with local municipalities
to meet the center's infrastructure needs. That work included
new roads, utilities, power feeds and telecommunication wiring.
Fannie Mae incorporated new technologies into the design
and construction, and Holder succeeded in constructing a U.S.
Green Building Council LEED-certified data center. Data centers
require significant electrical loads to provide adequate support
for computers and redundancy, making them more difficult to
certify under LEED guidelines.
The Fannie Mae data center has a 2N, dual, uninterrupted
power supply to ensure critical operations will not shut down
if an equipment failure occurs on any component in the facility.
A 70,000-sq.-ft. central plant supports the computer rooms
and contains 10 generators, six chillers and cooling towers,
27 air handling units, 30 uninterrupted power supply modules
and a 175,000-gallon thermal storage tank.
To compensate for the high electrical loads, Holder exceeded
standards in other areas, such as using brick originally installed
at Fannie Mae's 1950s-era headquarters. Masons mixed older
bricks with new bricks produced at the same plant as the original
brick.
Holder upheld Fannie Mae's original goal to create a team,
facilitate open communication and foster a do-what-it-takes
culture. A third party evaluated strengths and weakness midway
through the project, which allowed for midcourse corrections.
By pulling together, Holder overcame expected and unexpected
obstacles to bring the project in on time and within budget.
Owner: Fannie Mae
Project Director: Holder Construction
MEP Engineer: EYP Mission Critical
Group
Architect: Gensler
IT Consultant: CS Technology
Owner's Rep: Mark G Anderson
Civil Engineer: Rodgers Consulting
Structural Engineer: Hayes Whaley
Associates
Electrical: Truland Systems Corporation
Mechanical: Poole & Kent Company
Drywall: "Ceilings and Partitions,
Inc."
Exterior Stone: Espina Stone Company
Masonry: "Genco Masonry,
Inc."
Structural Steel: "Strait
Steel, Inc"
Precast Structure: Tindall Corporation
Data Cabling: Texel Corporation
Click here for the Office-Award
of Merit for Woodglen Park I
Return to Categories List
|