|
Parking Garage- Award of Merit
Kennedy Krieger Institute
Baltimore, Md.
Each
year, Baltimore's Kennedy Krieger Institute's world-renowned
treatment, education and research programs help more than
11,000 children and adolescents born with pediatric developmental
disabilities.
As the demand for the institute's services has grown, so
has the need for additional facilities. The institute has
prepared a multiphase building strategy that will add new
outpatient and inpatient hospitals, an MRI lab and office
space.
Given the limited availability of parking in the crowded
East Baltimore neighborhood, however, the institute first
needed to construct a multistory parking structure to accommodate
the additional staff and patients who would use the planned
new facilities.
Time was of the essence. The seven-story 364,532-sq.-ft.,
single-helix garage had to be completed within 15 months in
order for the institute to fulfill its commitment to provide
additional parking for nearby Johns Hopkins University.
The project was in the contract bid/award phase when a tempting
opportunity to save both time and money came to light. General
contractor/construction manager Whiting-Turner of Towson,
Md., learned that its precast supplier had already fabricated
460 61-ft., 7-in. by 12-ft. double-tees for another project
that had been canceled.
Though slightly shorter than the original specifications
for the institute's parking garage, the existing double-tees
could be adapted to project with minor design modifications.
With the institute's approval, architect Richter, Cornbrooks
Gribble Inc. of Baltimore, Md., reduced the size of the parking
bays by 1.5 ft., preserving the facility's capacity and safety.
Along with making the available double-tees suitable for use
in the garage, the modifications reduced the project's overall
cost by $300,000.
Construction began in March 2003 with the demolition of
more than a dozen abandoned row homes and apartments to create
a 3.05-acre site for the garage's 52,000-sq.-ft. footprint,
temporary parking and construction staging areas. Underlying
the site was a mix of sand and clay, requiring the drilling
of more than 360 auger-cast piles to support the garage.
Construction proceeded through the winter of 2003-04, with
excessive moisture and high-winds complicating erection of
the structure's precast concrete panels. The project team
also implemented numerous last-minute design changes to help
the institute better manage the garage's operations, including
the addition of doorways in several precast panels, upgraded
lighting and electrical wiring, and new wayfinding signage.
Despite the design, time and weather problems, the Kennedy
Krieger Institute's new parking garage was completed on schedule
in early June. The project had a remarkable record of no injuries,
due in large part to rigorous daily safety inspections and
Whiting-Turner's ongoing internal program of safety and quality
incentives.
One judge said that the project could not have achieved
a better outcome. Given all the constraints, changes and opportunities,
"the owner saved money and the project came in on time,"
the judge said. "That's teamwork."
Owner:Kennedy Krieger Institute
Architect: "Richter Cornbrooks Gribble, Inc."
General Contractor: Whiting-Turner Contracting
Electrical: Blumenthal-Kahn Electric
Plumber: Denver-Elek
Masonry: "Henry J. Knott Masonry, Inc."
Cutting: Innovative Cutting
Roofing: Kirby Brothers
Miscellaneous Metals: Miscellaneous Metals
Painting & Wallcovering: M & M Painting Company
Drywall: Rough Carp." Thomas
A. Jacobs & Son Contracting
Landscaping: "William T. King, Inc."
Return to Categories List
|