|
Restoration - Project of the Year
B&O Railroad Museum Roundhouse
Baltimore, Md.
Restoring the historic B&O Railroad Museum roundhouse
in Baltimore, Md., would have been difficult under any circumstances,
but the structural damage caused by a sudden roof collapse
presented Century Engineering and the entire restoration team
with an unprecedented challenge.
Half
of the roundhouse's low roof - approximately 19,000 sq. ft.
- collapsed after the President's Day snowstorm in February
2003. Thousands of pounds of snow, slate shingles and wood
and iron roofing members were piled on top of the historic
rolling stock, locomotives and other museum exhibits.
The domed upper roof and half of the low roof remained intact,
but their stability was questionable. The brackets supporting
the girder trusses broke, which left the columns intact but
unbraced at the low roof level. Falling debris damaged several
I-beams and some of the X-bracing between the columns.
The collapsing structure snapped a 3-in.-diameter natural
gas line and a 6-in.-diameter sprinkler main. Water filled
a turntable pit below and flooded the museum. Additional water
from melting snow and heavy rain that followed the storm added
to the flooding problem, which compromised the bearings of
the turntable's pivot mechanism and saturated its decking
and timber framing.
Severed electrical conduits suspended from the roof exposed
the flooded museum to electrical current.
"It was like starting over after a bomb had gone off,"
said one judge. "There were huge construction issues
with this project that made it a real challenge for the team."
Engineers faced a number of obstacles, both immediate and
long-term. Unlike a typical project, this one started with
immediate and urgent concerns of public safety, building stability
and protection of museum artifacts. Working closely with the
owner and contractor, Century Engineering, which has an office
in Towson, Md., quickly evaluated the remaining structure
and produced designs for the multiple types of building stabilization
needed. The contractor, Whiting-Turner Contracting of Baltimore,
Md., was able to start work within a couple days of the collapse.
Once
efforts began to stabilize the structure and remove debris,
engineers' focus shifted to the design of the replacement
roof. The task was complicated by the century-old museum's
National Landmark status. The building's aesthetics would
have to remain unchanged, while substantial structural upgrades
would be required to stabilize the building and prevent future
failures.
The original design elements that contributed to the collapse
were eliminated, while historic design elements no longer
in use today were mimicked.
While the domed upper roof was still intact, questions remained
about its condition. Once the design for the low roof was
complete and construction had started, engineers inspected
and evaluated the upper roof. When it was evident that it
was in poor shape, many courses of action were considered,
including reinforcing members and building a secondary roof
above the existing roof.
The museum decided to replace the roof, which presented the
unique challenge of phasing the work with the ongoing reconstruction
of the lower roof. Careful sequencing of work by the contractor
resulted in a safe and efficient process and allowed the museum
to reopen in just 20 months.
The museum's landmark status complicated the design of the
roof structure. The roof would have to look the same as the
original roof built in 1884, but with considerably more capacity.
Further complicating matters, no engineering drawings existed
for the building, and the large amount of debris at the site
prohibited the use of manlifts that would have given designers
a closer look at the roof. Before the debris was cleared,
engineers examined the remaining structure with binoculars,
closely measuring and examining collapsed members.
Consultations with museum staff, architects and Maryland
Historical Society members resulted in a roof that is difficult
to distinguish from the original but with substantially more
capacity.
Preengineered wood replaces sawn lumber, A992 steel is used
instead of wrought iron, and revised web spacing on the main
frame members contribute to the new design.
The unconventional jobsite tested contractors as well. Because
a number of museum exhibits could not be removed from the
roundhouse during the demolition and construction process,
they had to be protected. Many locomotives and other rolling
stock were wrapped with ultraviolet-resisting fabric and enclosed
in plywood boxes with scaffolding-supporting plywood floors.
The limited capacity turntable in the center of the roundhouse
would not support the weight of most construction machinery,
so contractors had to stage manlifts, forklifts and other
equipment on a 20-ft. circular strip between the roundhouse's
columns and the turntable.
To reconstruct the upper roof, which was located immediately
above the turntable, crews had to remove the turntable's deck,
exposing two large steel girders with timber outriggers at
approximately 30 in. on center. Since the framing was not
strong enough to support scaffolding that would in turn support
the dome roof, crews crafted a complicated system of scaffolding
that was meticulously threaded around the turntable framing.
Owner: B & O Railroad Museum
Architect: Schamu Machowski Greco SMG Architects
Structural, Mechanical, Electrical, and Plumbing Engineer
& Survey: "Century Engineering, Inc."
Geotechnical Engineer: "Froehling & Robertson, Inc."
Prime Contractor: The Whiting Turner Contracting Company
Steel Erector: T Steel
Cast Iron Fabrication: Codd Fabricators
Steel Fabricator: DOVCO Industrial Fabricators
Electrical Contractor: Enterprise Electric
HVAC and Plumbing Contractor: Smith Mechanical
Misc. Metals Contractor: "Ackerman & Baynes, Formit
Steel"
Masonry Contractor: Caretti
Return to Categories List
|