|
Transit - Award of Merit
Blue Line Extension to Largo Metrorail
Prince George's County, Md.
For
the first time in its 25-year history, the Washington Metropolitan
Area Transit Authority used a design-build process to extend
its Metrorail system 3.1 mi. into Prince George's County,
Md., and it shaved two to four years off a typical design-bid-build
schedule.
"This is a signature project for transportation in
the Washington, D.C., area," said one of the judges.
"It was well managed, and the team utilized some interesting
subcontracting techniques to get the job done."
The design-build team, a joint venture named LGS, included
the Lane Construction Co. of Meriden, Conn.; Granite Construction
Inc. of Watsonville, Calif.; Slattery Skanska of Whitestone,
N.Y.; and lead design firm Jacobs Engineering of Pasadena,
Calif.
Washington Metropolitan Area Transit Authority began planning
the Blue Line extension to Largo during the mid-1990s and
awarded LGS a $218 million contract in 2002. It included civil
work, track work, traction power, mechanical, electrical,
communications and train controls and testing.
WMATA expected to open the line in December and is anticipating
daily ridership of about 30,000.
Clark-Kiewit Largo, a joint venture of Clark Construction
of Bethesda, Md., and Peter Kiewit Sons' Inc. of Omaha, Neb.,
received the $92 million contract for two transit stations
and support structures. LGS and Clark-Kiewit closely coordinated
work on the project.
The line work consisted of 11,200 ft. of cut-and-cover double-box
tunnel construction - with a concrete wall separating inbound
and outbound track - and 3,150 ft. of aerial structure.
Rather than using 3-in.-thick timber lagging and soldier
pile, WMATA's traditional shoring process, LGS placed 8-ft.-wide
by 20- to 30-ft.-deep, .75-in.-thick sheets of metal-plate
lagging through clay and sand-based soils for use as temporary
retaining walls.
Bulk earthmoving progressed without interruption to install
timber lagging. Crews used timber lagging in those places
where the metal-plate lagging failed to go in all the way
or was impossible because of utility crossings.
In another innovative aspect of the project, LGS convinced
WMATA to allow it to reduce the level of bracing in the cut
excavation to one bracing level for up to 30 ft. of depth.
The line passes through a wooded residential area with no
structures, streets or utilities in its path, so ground movement
and settlement did not present as great a concern as it normally
would.
LGS used a top-down direct fixation track construction to
speed construction. It also incorporated drainage into the
track slab, instead of below, which is WMATA's normal placement.
Crews placed tunnel-box rebar ahead of the tunnel traveler
form. A concrete maturity measuring device allowed stripping
of forms as quickly as possible.
The line uses jet fans instead of conventional tunnel ventilation
fans. The original design did not meet National Fire Protection
Association 130 standards, necessitating a redesign that affected
all areas of construction.
TSC/WSC Joint Venture, made up of Truland Systems Corp.
of Arlington, Va., and Walker-Seal Companies Inc. of Fairfax,
Va., was responsible for all of the electrical, traction power
and communications systems. LGS maintained control of the
power through the train-testing phase of the project.
Owner: Washington Metropolitan Area
Transit Authority
Design/Builder: "LGS Lane Construction Corp., Granite
Construction Inc., Slattery Skanska"
Design Services: Jacobs Civil Inc.
Design/Automatic Train Control: "L.K. Comstock &
Company, Inc."
Fabricated Metals: Continental Construction
F&I Bridge Steel: Genesis Steel Service
Mechanical Systems: "Joshua Construction, Inc."
Trackwork: "Balfour Beatty Rail Systems, Inc."
F & I Rebar: "Midasco, Inc."
Concrete Piling: MIDLANTIC Piling Inc.
Waterproofing: Prospect Waterproofing
Low Voltage/Traction Power:
Communication: Truland Systems/ Walker Seal JV
Click here for the Transit-Project
of the Year
Return to Categories List
|