|
Transit-Project of the Year
New York Avenue Infill Station
Washington, D.C.
A
team of construction professionals successfully added the
first new in-fill New York Avenue Metrorail station to the
Washington Metropolitan Area Transit Authority's Red Line,
while only briefly shutting down service.
"This design/build project is very cool," said
one of the judges. "The team had to work between two
operating centers. It's a great project."
SL, a joint venture of Slattery Skanska Inc. of Whitestone,
N.Y. and the Lane Construction Corp. of Meriden, Conn., received
the $84 million design-build contract for the station, a hiking
and biking viaduct and tie-ins to the existing WMATA Red Line
in June 2002. It was expected to finish on time in December.
The team had experience designing and building similar transit
projects in the Northeast, but this was one of WMATA's first
forays into design-build.
The undertaking represents the first new transit station
in the United States constructed between two existing and
operating transit stations. WMATA plans more in-fill stations.
The site, immediately adjacent to the Red Line and the Northeast
Corridor rail line between Washington, D.C., and Boston, presented
some significant challenges. The transit authority could not
afford to have its line down or inconvenience riders.
SL recommended a simple and easily constructed station,
using modular component techniques, prestressed and precast
concrete, mechanically stabilized embankment retaining walls,
composite deck and parapet prefabrication and casting techniques,
box-culverts and offsite manufacture of major components.
The job resulted in a completely new station design that
the transit authority will be able to adapt and replicate
at other locations.
Rather
than use WMATA's typical cast-in-place construction for the
major service and equipment rooms at both the north and south
ends of the station, the team used a precast concrete box-culvert
technology. The rooms house automatic train control equipment
and electrical, mechanical and HVAC systems and were located
within 20 ft. of live track.
The box-culvert cells were fabricated offsite, trucked to
the station during the day and erected in segments at night,
during regular track outages.
More than 10,400 sq. ft. of mechanically stabilized embankment
retaining walls support the service and equipment rooms and
portions of the new station, as well as the south access to
the adjacent Metropolitan Branch Trail, a viaduct and superstructure
for future hiking and biking access. Placing the MSEs required
no pile-supported foundations.
SL used a composite precast deck and parapet slab segments
to construct the viaduct superstructure for the trail. One
hundred twenty, 12.3-ton deck and parapet segments were manufactured
offsite in 8-ft., 3-in. lengths, complete with electrical
blockouts, anchorage angles, shear connector pockets and parapet
wall structures. Crews erected and post-tensioned the segments.
To provide access to the trail, SL ordered a precast structural
concrete stairway tower and solo elevator tower. Four precast
structural concrete stairways connect the main terminal with
the station platforms.
Rather than cast-in-place beams and girders for the station
superstructure, SL employed a modified American Association
of State Highway and Transportation Officials-style trapezoidal
box section, prestressed concrete girders, beams and architectural
arch-shape segments.
The system, similar to that used in highway bridge construction,
reduced the number of foundations, pier columns, cross girders
and related elements that were needed. In addition, the structural
support elements could be manufactured offsite, with better
quality controls, and staged for erection.
WMATA recently redefined the look of its station canopy
structures, replacing concrete with a heavy structural-steel
plate frame, metal roof and skylights. The New York Avenue
station, the first with the new design, required 1.1 million
lbs. of structural steel plate, 450 ft. long, spanning almost
45 ft. in width.
It arrived in nine segments ready for erection, which the
team coordinated around the Red Line's operating hours. Again,
offsite fabrication allowed for greater quality control and
space and time savings at the site.
In addition to building the new station, SL relocated an
80-year-old B & O Railroad bridge so it could be used
for a new inbound track way to the New York Avenue station.
Trains began crossing the relocated bridge in September. WMATA
expects about 6,600 people will use the station.
Owner: The Washington Metropolitan
Area Transit Authority WMATA
Design-Build Contractor: "Sl, A Joint Venture of Slattery
Skanska Inc.& The Lane Construction Corporation"
Engineering, Design, & Architectural: "Jacobs Sverdup
Civil, Inc."
Ornamental & Architectural Metals: Accent Architectural
Automatic Train Control Systems: "Alstom Signaling, Inc."
Concrete Forming Systems: "Conesco DOKA, LTD"
Glass Curtain Walls, Storefronts, and Door Systems: "Custom
Glass Services, Inc."
Track Work, Rail Systems, and Railroad Structures: "Delta
Railroad Construction, Inc."
Mechanical, HVAC, & Plumbing: "John J Kirlin, Inc./Utley
Mechanical JV"
Click here for the Transit-Award of
Merit
Return to Categories List
|