|
Keep on Truckin'
As Team Makes Its Way Through
a $2.56 Billion Program, Traffic Keeps Moving
By Debra Woods
Even though Interstate
95, the East Coast's primary north-south route, crosses the
Woodrow Wilson Memorial Bridge in Washington, D.C., officials
opted to build a replacement drawbridge.
|
|
|
The V-pier
design of the Woodrow Wilson Bridge serves functional
and aesthetic purposes.
(Photo credit: Woodrow Wilson
Bridge Project)
|
New dual-span drawbridges will replace the existing bridge,
which was completed in 1961, and will improve traffic flow
on the interstate between Virginia and Maryland. The replacement
bridge will cost $632 million. The entire $2.56 billion project
also includes highway and interchange improvements and should
be completed by spring 2008.
"We did studies to see if we could put in a high bridge,"
said Bob Healy, deputy director of the office of bridge development
for the Maryland State Highway Administration. "We could
make one fit, but that gave us some issues that were undesirable
as well. It would have required steep grades."
He added that a high bridge on I-95 would be detrimental
because of truck traffic.
Parsons Corp. with Mueser Rutledge consulting designed the
bridge to accommodate a future commuter rail system, and the
incline would have been difficult for trains. Also, Alexandria,
Va., officials felt a high span would be too intrusive. The
bridge crosses a park in that historic city.
Four cooperating agencies sponsored the project - the Federal
Highway Administration, Virginia Department of Transportation,
Maryland State Highway Administration and the District Department of Transportation.
Officials spent more than 10 years planning the 7.5-mi. replacement
structure and divided the project into multiple contracts.
It began with Weeks Marine Inc. of Cranford, N.J., dredging
a deeper navigation channel. That job was completed in 2001.
Then the foundation work was done by Tidewater Construction
Corp./Kiewit Construction Co./Clark Construction Group of
Virginia Beach, Va., which wrapped up in June.
When only one contractor submitted a bid for bridge construction,
transportation officials split the project into three contracts:
the drawbridge; the Maryland approach, primarily over water;
and the Virginia approach, mostly over land.
The Bascule A joint venture
of American Bridge/Edward Kraemer and Sons of Coraopolis,
Pa., received notice to proceed on its $186 billion, 600-ft.
bascule section of the bridge in February, 2003. Work began
on the southern, sixlane span in March 2003. When complete
in 2006, traffic will be routed to the new bridge. American
Bridge/Kraemer will demolish the existing structure and start
on the northern span.
Each bridge has a four-leaf bascule, which operates as if
it were four separate drawbridges, linked together. Normally,
they will rise simultaneously, but officials can lift them
independently to complete maintenance on one lane of the road
at time.
"It all has to fit closely and be able to lock together,"
Healy said.
The deck will consist of stainless-steel rebar and light
concrete. Officials chose stainless steel to prevent corrosion
and future deck replacements. The approaches and piers have epoxy-coated rebar.
"It's a massive structure," said Don Bell, project
manager for American Bridge/Kraemer. "The motor is not
that big. It's very well balanced and engineered."
The bridge tender will operate the bascule from a seven-story,
structural-concrete and curved, glazed-glass curtain wall
operator's house, which is designed to look like a ship's
tail section.
Transportation officials wanted an arch bridge, but soil
conditions precluded it. So Parsons designed a structure with
arch ribs and V-shaped supporting piers. The system has functional
benefits and also creates an aesthetically pleasing appearance.
"Our concept was to use a V-pier, which minimized the
bending in the foundation and tremendously reduced the amount
of piling and substructure that was required," said Craig
Finley, senior vice president of Parsons and bridge and tunnel
division manager.
"This project has a steel superstructure, which is light
and reduces the weight for the foundations."
Concrete and Steel About
45 craftsman and 12 supervisors were working on the first
of four piers in November.
American Bridge/Kraemer built a floating-pontoon access bridge
from the Virginia shore to the jobsite, which it uses to transport
workers and small materials.
Barges bring the steel and heavier components. Concrete is
pumped from shore using a permanent slick line.
The piers' lower portions, about 90 ft. high, are hollow,
cast-in-place concrete. Near the bascule machinery, the piers
become solid concrete. Everything is post-tensioned.
"It's one of the most difficult angles all of us have
seen," Bell said. "This is about a 45-degree angle, and that's a special challenge for
the workers."
Chuck Mathers, vice president of Veterans Steel Services
Inc. of Elkridge, Md., said it's like working on a Stairmaster
all day. His firm will furnish and place approximately 5,000
tons of reinforcing steel, including the 1,200 tons of stainless
steel for the deck.
Ironworkers from Veterans began fabricating on the pier but
found it too complex. They now prefabricate most cages on
a work platform at the base of the pier, and the walls are
then lifted into place and secured.
"This is the only portion of the bridge where they are
going to fabricate the steel, place it and pour the concrete,"
Mathers said. "The other portions of the bridge are precast."
American Bridge/Kraemer is using EFCO forms with a traveler
system to build the hollow core. The system gives the company
flexibility in moving the forming system. Each segment takes
two weeks to complete. Custom falsework supports the concrete
until it strengthens and is post-tensioned.
American Bridge/Kraemer will set several bascule girders
using twin lifts during the summer. The bridge tender's tower
is also on track for a summer start.
"We've only been here for a seven-month period and
have made good progress," Bell said.
Return
to List
|